The Sail @ Marina Bay

Meinhardt’s Engineering Innovations

1 Massing of the two towers was carefully planned to avoid the MRT tunnels and allow necessary safe basement construction.   
  
2 Residential units were arranged on both sides of the central corridor to create a parallel-coupled-shearwall system. The innovative framing resulted in excellent structural performance without compromising functionality and architectural design. 
3 The use of modular and repetitive structural framing comprising an optimum mix of pre-cast and in-situ construction, reduced the construction period of each floor. 

 