Gardens by the Bay, Bay South

Meinhardt's Engineering Innovations

1.  Together with the main contractor, Meinhardt introduced a detailed construction sequence to ensure that the façade steel works and gridshell were structurally stable throughout the erection and also minimised the built-in stresses of the gridshell and arches interface.

 stages

2.  Non-standard sections were used for the arches and the gridshell members of the steel conservatories. This required extensive analysis and rigorous design checks.